Rail Baltica construction progress at RIX Riga Airport | May 2026

In the first half of 2026, Rail Baltica construction works at RIX Riga Airport have continued across a wide area — from the demolition of the cargo centre hangar to the construction of viaduct structures. In this video, we take a look at the progress achieved so far: • the cargo centre hangar on Ziemeļu Street has been demolished; • the installation of 147 weathering steel beams has been completed along a 500-metre section from the station building to Ziemeļu Street; • installation of reinforced concrete side shielding elements has started; • works are continuing next to the airport’s 4th apron construction site, including the construction of piles and supports. Take a look at the latest Rail Baltica construction progress at RIX Riga Airport!