Tóm tắt quan trọng Nghị định 206 năm 2026 NĐ-CP về Quản lý chi phí đầu tư xây dựng BIM xây dựng 360
Decree 206/2026/ND-CP on the Management of Construction Investment Costs This is an important document on the management of construction investment costs, focusing on: preliminary total investment cost, total investment cost, construction estimate, bid package estimate, bid package price, construction norms, construction price, construction price index, project management costs, consulting costs, other costs, and the responsibilities of relevant parties. A very important point: Decree 206 does not regulate contract prices, contract payments, contract settlements, or investment capital payments and settlements. These contents fall under separate regulations on contracts, payments, and settlements. 1. Scope of Application The Decree primarily applies to public investment projects, PPP projects, projects using recurrent expenditures from the state budget, and other state budget projects not within the scope of public investment. Other projects may refer to this for cost determination and management, but they must take responsibility for their own decisions. 2. Principles of Cost Management Construction investment costs must be determined according to the project, work, item, and package; and must be consistent with the design, standards, regulations, technical guidelines, technology used, progress, quality of the work, and price levels at the time of cost determination. For public investment projects, the decree emphasizes decentralization, delegation of authority, and increased responsibility of the investor; the investment decision-maker has the role of checking and supervising cost management. 3. Total Investment Amount as a Cost Ceiling The total construction investment amount after approval is the maximum cost for the investor to implement the project. The total investment amount includes: compensation, support, and resettlement costs; construction costs; equipment costs; project management costs; and consulting costs. Other costs and contingency costs. It is important to note that compensation, support, and resettlement costs are quite broad, including those related to land, water resources, forest land conversion, reforestation, rice paddy protection, infrastructure relocation and restoration, etc. If this cost group is omitted, the project is very likely to have an underestimated total investment. 4. Preliminary Total Investment and Construction Estimate The preliminary total investment is determined based on the scale, capacity, preliminary design plan, investment capital rate, cost rate, work group price, component price, structural unit price, and cost data of similar projects. For large projects with complex techniques and new technologies not yet common in Vietnam, foreign data may be referenced, but it must be analyzed and converted to the price level and implementation conditions in Vietnam. The construction estimate must adhere to the detailed design after the project is approved. The cost estimate is not just about calculating quantities and multiplying by unit prices, but must be based on the design, construction methods, construction conditions, schedule, market prices, price index, and valid cost data. 5. Construction Package Price The package price is the value of the package approved in the contractor selection plan, including all necessary costs to execute the package, including contingency costs, fees, charges, and taxes. The package price must be updated according to the law on bidding, avoiding discrepancies between the total investment, cost estimate, and package price. 6. Construction Norms, Prices, and Price Index The system of construction norms, construction prices, material prices, labor prices, construction machinery prices, equipment prices, construction price index, and the national database on construction activities are important bases for determining the total investment, cost estimate, and package price. A key point is that price data must be updated, published, and used from the correct source. Using outdated prices, norms, or inappropriate price indices can easily lead to errors in cost assessment, auditing, or adjustment. 7. Assessment, Verification, Approval, and Adjustment The Decree clearly stipulates the assessment, verification, and approval of total investment costs, estimates, and cost adjustments. The aspects to be controlled include: whether the documentation is complete and valid; whether the legal basis is correct; whether the quantity, type, and number of equipment conform to the design; whether the prices, norms, and price indices are appropriate for the time and market; the reasons for cost increases or decreases; and whether the adjustment changes the project's objectives, scale, location, or effectiveness. 8. Major Risks in Application The most dangerous errors include: confusion between cost management and contract management; omission of costs for land, environment, forests, rice, and water resources; and estimates that d...

Summary of Key Provisions in Decrees 206, 207, 209, and 210 Regarding Cost and Contract Management

Nghị định 217/2026/NĐ-CP quy định chi tiết một số điều của Luật Xây dựng về quản lý HĐXD

Hướng dẫn lập dự toán theo thông tư 36 và thông tư 37 với thông tư 38 có hiệu lực 1 tháng 7 năm 2026

Cheating in Tuyen Quang. Teacher enters exam room to provide answers. Should they retake the exam...

TỔNG HỢP CÁC NGHỊ ĐỊNH HƯỚNG DẪN LUẬT XÂY DỰNG SỐ 135/2025/QH15(NĐ 206; NĐ 207; NĐ 209; NĐ 210..VV)

Học BIM Manager BIM Coordinator Các quy định pháp luật trong thực hiện BIM xây dựng Phần 2 CDE 360

BREAKING NEWS | WHY ARE MUNICIPAL MERGERS STILL NECESSARY AND WHAT IS THE PROCESS? | #news

1970s Inspired French Pop | Warm Retro Nostalgia | Slow Cafe Moments (60s 70s 80s)

The Great Infrastructure Paradox: Is Long Thanh Airport Headed for the Same Fate as the New Mien ...

The Vietnamese Boom Is a Lie (and it's worse than you think)

Overview of Decree 212/2026: Key Essentials for BIM Construction 360

Circular 32/BXD guiding Decree 207/2026 on construction quality management and maintenance

1970s French Retro Chanson | A Timeless Dream | Slow Cafe Moments (60s 70s 80s)

DỰ THẢO SỬA ĐỔI LUẬT ĐẤT ĐAI: PHÂN TÍCH, ĐÁNH GIÁ TÁC ĐỘNG? | Tài chính BĐS

Decoding Decree 206/2026 detailing regulations on construction investment cost management for Law...

Key Summary of Decree 207/2026/ND-CP on Construction Quality Management, Execution, and Maintenance

Essential Summary of Decree 217/2026/ND-CP on Construction Management by BIM Construction 360

Cuộc Sống Anh Trai Sau Khi Bị Trục Xuất Từ Mỹ Về Việt Nam

SO SÁNH ĐIỂM MỚI NGHỊ ĐỊNH 206/2026/NĐ-CP và NGHỊ ĐỊNh 10/2021/NĐ-CP Chính phủ

