Rail Baltica Raplamaa mainline section I (part I - 29.04.2026)

CURRENT WORKS: Final sections of the embankment being prepared for the frost protection layer and ditches getting their final shape. First works on CCS connection chambers are also visible. GENERAL INFORMATION: First part of Rail Baltica Raplamaa section I from the border of Rapla county until future Härjaoja viaduct (Pk 0+000 - Pk 3+900) or about 3,9 km. Flight with Mavic 3 at an altitude of 40 meters. LANDMARKS: Tagadi viaduct (first viaduct) has been completed under an earlier contract as well as Urge ecoduct (second viaduct). The flight terminates shortly after Urge ditch with a view to Urge local road, where the future Härjaoja viaduct will be constructed.