Southbound and down

Off on a nice clean motorway job this time, bits of it were holding too much water during heavy rains so parts where to be lifted and cambered more to make the water shed faster, this involved removing some existing channel kerb and a new kerb line installed higher up to tie in with the new camber, some drainage repairs and upgrades where being carried out at the same time and in this video its just getting the trench boxes off the lorry, built up ready to use and then later ferrying them up to where the drainage job was to start, theres also some topsoil to peel back and relocate to go in behind where the new kerb line is going to be higher so that got placed in behind against the barrier and sealed up til later when the kerbs are in