Chuck E. Cheese Remodel Process - Florence, KY

Filmed throughout the remodel. This was a 42 day process that reimagined the atmosphere of Chuck E. Cheese to the "CEC 2.0" remodel- new art, flooring, games, and most importantly, the removal of animatronics in favor of a dance floor and video wall. Chapters: 0:00 Day Before Remodel 0:12 Day 1 - Remodel Starts 0:20 Day 2 1:44 Day 4 2:18 Day 6 3:42 Day 10 5:19 Day 12 7:03 Day 13 9:28 Day 19 - Show Removed 10:44 Day 20 13:54 Day 21 14:24 Day 22 16:34 Day 28 18:19 Day 23 - Exterior Finished 18:45 Day 41 - Video Wall Installed, New Games 20:35 4/25/22 - Remodel Complete 21:06 Grand Reopening 21:22 Conclusion Special thanks to ‪@ChuckEEntertainment‬, ‪@CECFanOffical‬, and ‪@pizzatimemedia‬ for photos!