Finishing Hillside Excavation and Starting Duct Bank Installation | Day 10

Day 10 of the Campbellsville Raw Water Intake (RWI) Upgrade completes the major hillside excavation and begins installing the electrical duct bank down toward the lake. After cutting a path through steep terrain, we started laying PVC conduits and preparing the route for underground electrical infrastructure. This phase transitions the project from excavation into installation as progress continues downhill. The next stage will continue duct bank installation and further development of the electrical pathway to the intake system. Real jobsite work from Gardner Electric documenting the project from start to finish. #heavyequipment #excavation #construction #undergroundelectrical #ductbank #jobsite #infrastructure #tradesman #gardnerelectric