Roseville High School Modernization - 07/10/2026

Happy Friday Everyone!!!! Roseville High ended the week with an exciting concrete pour to mark the start of the radius concrete work on the south end of the project, and it looks great. Earthwork crews continued placing and grading AB throughout the site, with concrete forms being built behind them. On the exterior of the building, lath installation continued and has progressed to the West and South elevations. Scratch coat followed closely behind with the North and East elevations nearing completion. Inside the building, drywall crews continued sanding and finishing the first-floor drywall in preparation for paint. The elevator installation remains in progress. Have a great weekend everyone!!!