Hi, work has continued on the Köpenick train station renovation. Both connecting curves from the outer ring towards Köpenick are now connected to the new freight bypass track. Part of the overhead line on this track is already in place. The old track towards Ostbahnhof (East Station) no longer has any overhead line. Some of the overhead line masts have also been removed. From mid-August, traffic to and from Frankfurt/Oder will run via the new freight bypass track. Hi, the work on the train station renovation in Köpenick has continued. Both connecting curves from the outer ring towards Köpenick are now connected to the new freight bypass track. Part of the overhead line on this track is already installed. On the old track towards Ostbahnhof, there is no longer any overhead line. Some of the overhead line masts have also been removed. So from mid-August, traffic to and from Frankfurt/Oder will run via the new freight bypass track.