Laying on gravel - Novoceram Outdoor Plus

Lay the tiles on gravel to obtain an even surface with minimal joints of 5mm even on large areas, guaranteeing excellent rainwater run-off. Steps: 1/ Level the substrate with a rake. 2/ Place a layer of non-woven fabric on the substrate. 3/ Spread an even layer of at least 5-10 cm of gravel (16-35 mm). For even better adherence of the slab, you can add a layer of lime to the gravel. 4/ Level the substrate with a rake. 5/ Spread a layer of at least 5.10 cm of fine gravel (4-6 mm). 6/ Level the surface using a spirit level. 7/ Lay the slabs with spacer crosses of at least 5 mm to allow excellent drainage of rainwater. During laying continually check the planarity of the surface. 8/ Novoceram Outdoor Plus slabs installed onto gravel can be walked on immediately after laying. More about Novoceram Outdoor Plus : http://www.novoceram.com/products/cli... More about Laying on Gravel : http://www.novoceram.com/products/cli...